Lock-up inspection in Werribee

The house is closed in and the plasterer is next. This is the last look at insulation, ducts, sarking and the services inside the walls.

  • With roof, windows, external doors and cladding on, before plasterboard
  • 1 to 2 hours on site
  • Report within 24 hours
Request a Werribee quoteChoose the inspection, leave your details and we will call you back.

No obligation. We use your details for your quote and may contact you about it even if you don't finish.

Fully licensed & accredited

Stage4 of 7
When to bookWith roof, windows, external doors and cladding on, before plasterboard
Time on site1 to 2 hours on site
Inspected againstAS 3700 (masonry), AS 4773, AS 2047 (windows), NCC Part 3.5 roof and wall cladding, manufacturer flashing details

What is included in a Werribee lock-up (pre-plaster) inspection

  • Wall wrap and roof sarking coverage, laps and tears
  • Head, sill and jamb flashings to every window and door
  • Weep holes clear and correctly spaced
  • Articulation joints and cavity clearance
  • Mortar joints, brick ties and bed joint reinforcement
  • Lintels over openings and their bearing
  • Roof battens, tile or sheet fixing and ridge details
  • Valleys, penetrations and box gutter supports
  • Roof space insulation, sarking and services
  • Exhaust and rangehood ducting runs
  • External cladding fixing and clearance to ground
  • Garage, porch and alfresco set-downs
  • Site drainage and grading before landscaping
  • Debris and mortar droppings at the slab edge
Why it matters here

Lock-up (pre-plaster) inspections on Werribee builds

Lock-up on Werribee builds tends to catch services and insulation rather than structure: ducts crimped in the roof space, batts missing from walls, sarking left off a tiled roof and a sewer junction placed inside its clear zone.

What we find at this stage in Werribee

  • Ducts crimped or bent too tightly
  • Wall batts missing or gapped
  • No sarking under a tiled roof
  • Sewer junction inside the 450mm zone
  • Gutters holding water
  • Upper floor sheets squeaking
Water lying in the gutter where it lacks enough fall to drain, found during a lock-up inspection in Werribee
Water lying in the gutter where it lacks enough fall to drain
Insulation missing from a wet area wall before the linings go up, found during a lock-up inspection in Werribee
Insulation missing from a wet area wall before the linings go up
Sample findings

Sample defects found during our lock-up (pre-plaster) inspections in Werribee

Annotated findings from Lock-up (pre-plaster) inspections.

Heating ducts crimped and tightly bent in the roof, choking airflow to rooms, found during a lock-up inspection in Werribee
Heating ducts crimped and tightly bent in the roof, choking airflow to rooms
Wall batts missing in places with the plasterer about to start, found during a lock-up inspection in Werribee
Wall batts missing in places with the plasterer about to start
Sarking not installed beneath the tiled roof at lock-up stage, found during a lock-up inspection in Werribee
Sarking not installed beneath the tiled roof at lock-up stage
Sewer junction placed inside the 450mm clear zone meant to prevent blockages, found during a lock-up inspection in Werribee
Sewer junction placed inside the 450mm clear zone meant to prevent blockages

The other stages of a Werribee build

  1. Bored piers inspection in Werribee1Bored piersAfter the holes are drilled and the cages set, before concrete goes in
  2. Slab pre-pour inspection in Werribee2Slab pre-pourOnce pods, steel and membrane are down, the day before concrete
  3. Frame inspection in Werribee3FrameWhen walls, trusses and roof cover are up, before any sarking or insulation hides them
  4. Fixing inspection in Werribee5FixingWhen doors, skirtings and cabinetry are in, ahead of the painter
  5. Waterproofing inspection in Werribee6WaterproofingAfter the membrane has cured and before the tiler arrives
  6. Pre-handover (PCI) inspection in Werribee7Pre-handover (PCI)Roughly a week before the builder hands over the keys

All construction stage inspections in Werribee →

Guides

Construction stage guides for Werribee

All guides →

Book a lock-up (pre-plaster) inspection in Werribee

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Lock-up (pre-plaster) inspections in Werribee: common questions

Why look at insulation before plaster?

Because a missing batt cannot be seen once the wall is lined, and gaps reduce the energy rating the home was designed to achieve.

What does a crimped duct do?

It restricts the air reaching that room, so the heating and cooling work harder for less effect.

Do you check frame items again at lock-up?

Yes. Anything still open from the frame report is looked at again and recorded as fixed or not fixed.

Is sarking always required?

That turns on the roof type, the lot's wind class and what your specification calls for. Where it is specified and missing, we record it for the builder to confirm.

Do you test the plumbing at this stage?

No. We look at visible pipework and junction positions; pressure testing belongs to the plumber.

How long after the inspection can plaster go on?

As soon as the items are fixed. Send the report to the supervisor the day you receive it.